Grid infrastructure βΊ Connection queue βΊ Wind + storage
WIND + STORAGE Β· SHETGlen Lednock
Glen Lednock is a 165 MW wind + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Glen Lednock 132kV Substation, with capacity due from November 2031. The connection agreement is held by Glen Lednock Wind Farm Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Nov 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004520
- Customer
- Glen Lednock Wind Farm Limited
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 165 MW
- Change in this agreement
- +165 MW
- Capacity effective from
- 30 November 2031
- Connection site
- Glen Lednock 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem