Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · SHETGalileo 12 Limited
Galileo 12 Limited is a 151 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Fetteresso 132kV substation, with capacity due from October 2033. The connection agreement is held by Galileo 12 Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004804
- Customer
- Galileo 12 Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar), Wind Onshore
- Total capacity
- 151 MW
- Change in this agreement
- +151 MW
- Capacity effective from
- 31 October 2033
- Connection site
- Fetteresso 132kV substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Fetteresso 132kV substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem