Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · SHETBalvedavist 162 Battery Storage
Balvedavist 162 Battery Storage is a 162 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Spittal 132kV Substation, with capacity due from October 2030. The connection agreement is held by S4N Spittal Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002024
- Customer
- S4N Spittal Ltd
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 162 MW
- Change in this agreement
- +162 MW
- Capacity effective from
- 31 October 2030
- Connection site
- Spittal 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Spittal 132kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem