United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8818.0 GW
Active in queue18.0 GW88 requests
Agreement signed1,905 MW13 requests
Withdrawn10331.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

88 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 418, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jan 2022target 2026
Onshore wind project Company MY, Lassen County
Onshore wind
715 MWPaused / redesign Lassen, CAWest Mar 2022target 2032
Onshore wind project J2841, Independence County
Onshore wind
500 MWIn study Independence, ARMISO Sep 2022target 2025
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Bug Tussle Wind Project
Onshore wind ยท Bug Tussle Wind, LLC
397 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Lake Henry Wind
Onshore wind
305 MWPaused / redesign Kent, TXERCOT Sep 2022target 2027
Academy Wind
Onshore wind
305 MWPaused / redesign Dickens, TXERCOT Sep 2022target 2028
Triangle Ranch Alpha
Onshore wind ยท Triangle Ranch Wind
302 MWIn study Cottle, TXERCOT Oct 2022target 2029
Onshore wind project J2369, Taylor County
Onshore wind
300 MWIn study Taylor, IAMISO Sep 2022target 2030
LA300W
Onshore wind
300 MWPaused / redesign Luna, NMWest Mar 2022target 2028
Onshore wind project AH2-270, Whiteside County
Onshore wind
300 MWIn study Whiteside, ILPJM Mar 2022target 2026
Onshore wind project NC5-009, Mohave County
Onshore wind
300 MWIn study Mohave, AZWest Apr 2022target 2027
Onshore wind project J2613, Jackson County
Onshore wind
300 MWIn study Jackson, ARMISO Sep 2022target 2025
Onshore wind project Company NA, White Pine County
Onshore wind
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Onshore wind project 118, Apache County
Onshore wind
300 MWIn study Apache, AZWest Apr 2022target 2025
Onshore wind project J2436, Webster County
Onshore wind
300 MWIn study Webster, IAMISO Sep 2022target 2030
Onshore wind project G0761, Grant County
Onshore wind
290 MWIn study Grant, WAWest Jun 2022target 2026
Crossroads Wind
Onshore wind ยท HyFuels Green Lake Wind LLC
277 MWAgreement signed Victoria, TXERCOT Sep 2022target 2027
Onshore wind project J3078, Peoria County
Onshore wind
252 MWIn study Peoria, ILMISO Sep 2022target 2026
Onshore wind project IA-PNM-2023-01, Cibola County
Onshore wind
250 MWIn study Cibola, NMWest Oct 2022target 2025
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Onshore wind project Q458, Navajo County
Onshore wind
242 MWIn study Navajo, AZWest Mar 2022target 2026
Onshore wind project J2342, Worth County
Onshore wind
230 MWIn study Worth, IAMISO Sep 2022target 2027
Rubicon Echo Wind
Onshore wind
228 MWPaused / redesign Haskell, TXERCOT May 2022
Rubicon Alpha Wind
Onshore wind ยท Throckmorton Wind, LLC
226 MWAgreement signed Haskell, TXERCOT May 2022target 2027
Onshore wind project C2-92, Bingham County
Onshore wind ยท PacifiCorp
206 MWIn study Bingham, IDWest May 2022target 2026
Onshore wind project MPC04400, Grand Forks County
Onshore wind
206 MWIn study Grand Forks, NDMISO Feb 2022target 2024
Triangle Ranch Bravo
Onshore wind ยท Triangle Ranch Wind
200 MWIn study Cottle, TXERCOT Oct 2022target 2028
Triangle Ranch Charlie
Onshore wind
200 MWPaused / redesign Cottle, TXERCOT Sep 2022target 2025
Onshore wind project BHBE G17, Campbell County
Onshore wind
200 MWAgreement signed Campbell, WYWest Mar 2022target 2026
Onshore wind project J2332, Cottonwood County
Onshore wind
200 MWIn study Cottonwood, MNMISO Sep 2022target 2027
Onshore wind project J2049, Shelby County
Onshore wind
200 MWIn study Shelby, ILMISO Mar 2022target 2025
Onshore wind project J2990, Pottawattamie County
Onshore wind
200 MWIn study Pottawattamie, IAMISO Sep 2022target 2025
Onshore wind project BHBE G21, Campbell County
Onshore wind
200 MWAgreement signed Campbell, SDWest Aug 2022target 2025
Onshore wind project J2641, Jackson County
Onshore wind
200 MWIn study Jackson, ARMISO Sep 2022target 2025
Onshore wind project J2614, Henry County
Onshore wind
200 MWIn study Henry, ILMISO Sep 2022target 2026
Onshore wind project J1926, Tazewell County
Onshore wind
200 MWIn study Tazewell, ILMISO Mar 2022target 2025
Onshore wind project 120, Cochise County
Onshore wind
200 MWIn study Cochise, AZWest May 2022target 2025
Onshore wind project J2563, Cottonwood County
Onshore wind
200 MWIn study Cottonwood, MNMISO Sep 2022target 2026
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Onshore wind project AI1-168, Coshocton County
Onshore wind
200 MWIn study Coshocton, OHPJM Sep 2022target 2027
Onshore wind project J2577, Cross County
Onshore wind
200 MWIn study Cross, ARMISO Sep 2022target 2025
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Onshore wind project AI1-191, Stephenson County
Onshore wind
200 MWIn study Stephenson, ILPJM Sep 2022target 2027
Onshore wind project G0819, Douglas County
Onshore wind
200 MWIn study Douglas, WAWest Nov 2022target 2027
Onshore wind project J2930, Henderson County
Onshore wind
200 MWIn study Henderson, KYMISO Sep 2022target 2025
Onshore wind project J2989, Hardin County
Onshore wind
200 MWIn study Hardin, IAMISO Sep 2022target 2025
Onshore wind project J2346, Murray County
Onshore wind
200 MWIn study Murray, MNMISO Sep 2022target 2027
Onshore wind project J2963, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Sep 2022target 2025
Onshore wind project GI-DISIS-2022-29, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest May 2022target 2029
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)