United States › Grid › Interconnection queues › New Mexico

ONSHORE WIND · WEST

Onshore wind project IA-PNM-2023-01, Cibola County

Onshore wind project IA-PNM-2023-01, Cibola County is a 250 MW onshore wind request in interconnection study in the West interconnection queue, in Cibola County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusIn planning
  1. PlanningQueued Oct 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IA-PNM-2023-01
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Ambrosia Lake - West Mesa 230 kV Line
Location
Cibola County, New Mexico
Technology
Wind: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
21 October 2022
Proposed online date
December 2025

Location

Marker shows the centre of Cibola County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Cibola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem