Solar + storage project IA-PNM-2023-29, Cibola County

Solar + storage project IA-PNM-2023-29, Cibola County is a 80.0 MW solar + storage request withdrawn in the West interconnection queue, in Cibola County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2023-29
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Marquez 115 kV Substation
Location
Cibola County, New Mexico
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
29 September 2023
Proposed online date
April 2029

Location

Marker shows the centre of Cibola County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Cibola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem