Solar project SGI-PNM-2014-03, Cibola County

Solar project SGI-PNM-2014-03, Cibola County is a 10.0 MW solar request built and operating in the West interconnection queue, in Cibola County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Jan 2014 (completed)
  2. ConsentedJul 2014 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2014-03
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM GPD Marquez Substation Feeder 11
Location
Cibola County, New Mexico
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 7/11/2014.
Queue status
Operational
Entered queue
15 January 2014
Agreement signed
11 July 2014

Location

Marker shows the centre of Cibola County; the queue data does not give exact sites.