United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTTriangle Ranch Charlie
Triangle Ranch Charlie is a 200 MW onshore wind request suspended in the ERCOT interconnection queue, in Cottle County, Texas.
Queue statusPaused / redesign
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0179
- Grid region
- ERCOT (Texas)
- Location
- Cottle County, Texas
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Queue status
- Suspended
- Entered queue
- 14 September 2022
- Proposed online date
- August 2025
Location
Marker shows the centre of Cottle County; the queue data does not give exact sites.
Other requests in Cottle County
- Solar project GEN-2018-015, Cottle CountySolar · 252 MW · agreement signed
- Triangle Ranch AlphaOnshore wind · 302 MW · in study
- Solar project GEN-2024-317, Cottle CountySolar · 300 MW · in study
- Soluce Cotton SolarSolar + storage · 203 MW · in study
- Soluce Cotton StorageSolar + storage · 202 MW · in study
- Triangle Ranch BravoOnshore wind · 200 MW · in study
- Triangle Ranch DeltaOnshore wind · 102 MW · suspended
- Triangle Ranch EchoOnshore wind · 101 MW · suspended
- Triangle Ranch FoxOnshore wind · 101 MW · suspended
- Battery storage project GEN-2023-228, Cottle CountyBattery storage · 250 MW · withdrawn
- Comet SolarSolar · 152 MW · withdrawn
- Obsidian SolarSolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem