United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTComet Solar
Comet Solar is a 152 MW solar request withdrawn in the ERCOT interconnection queue, in Cottle County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2022 (completed)
- Withdrawn / abandonedDec 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0158
- Grid region
- ERCOT (Texas)
- Developer
- Milky Way Power LLC
- Connection point (POI)
- Tap 138 kV 6030 West Childress - 6135 Paducah Clare Street
- Location
- Cottle County, Texas
- Technology
- Solar: 152 MW
- Total requested
- 152 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 19 January 2022
- Proposed online date
- December 2025
- Withdrawn
- December 2023
Location
Marker shows the centre of Cottle County; the queue data does not give exact sites.
Other requests in Cottle County
- Solar project GEN-2018-015, Cottle CountySolar Β· 252 MW Β· agreement signed
- Triangle Ranch AlphaOnshore wind Β· 302 MW Β· in study
- Solar project GEN-2024-317, Cottle CountySolar Β· 300 MW Β· in study
- Soluce Cotton SolarSolar + storage Β· 203 MW Β· in study
- Soluce Cotton StorageSolar + storage Β· 202 MW Β· in study
- Triangle Ranch BravoOnshore wind Β· 200 MW Β· in study
- Triangle Ranch CharlieOnshore wind Β· 200 MW Β· suspended
- Triangle Ranch DeltaOnshore wind Β· 102 MW Β· suspended
- Triangle Ranch EchoOnshore wind Β· 101 MW Β· suspended
- Triangle Ranch FoxOnshore wind Β· 101 MW Β· suspended
- Battery storage project GEN-2023-228, Cottle CountyBattery storage Β· 250 MW Β· withdrawn
- Obsidian SolarSolar Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem