United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-228, Cottle County
Battery storage project GEN-2023-228, Cottle County is a 250 MW battery storage request withdrawn in the SPP interconnection queue, in Cottle County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-228
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Tuco-Okalunion 345 kV line
- Location
- Cottle County, Texas
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2026
- Withdrawn
- August 2025
Location
Marker shows the centre of Cottle County; the queue data does not give exact sites.
Other requests in Cottle County
- Solar project GEN-2018-015, Cottle CountySolar Β· 252 MW Β· agreement signed
- Triangle Ranch AlphaOnshore wind Β· 302 MW Β· in study
- Solar project GEN-2024-317, Cottle CountySolar Β· 300 MW Β· in study
- Soluce Cotton SolarSolar + storage Β· 203 MW Β· in study
- Soluce Cotton StorageSolar + storage Β· 202 MW Β· in study
- Triangle Ranch BravoOnshore wind Β· 200 MW Β· in study
- Triangle Ranch CharlieOnshore wind Β· 200 MW Β· suspended
- Triangle Ranch DeltaOnshore wind Β· 102 MW Β· suspended
- Triangle Ranch EchoOnshore wind Β· 101 MW Β· suspended
- Triangle Ranch FoxOnshore wind Β· 101 MW Β· suspended
- Comet SolarSolar Β· 152 MW Β· withdrawn
- Obsidian SolarSolar Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem