OCTARY USA ยท INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5310.4 GW
Active in queue10.4 GW53 requests
Agreement signed1,981 MW9 requests
Withdrawn7921.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

53 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project C1-35, Carbon County
Onshore wind ยท Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project NC5-008, Mohave County
Onshore wind
500 MWIn study Mohave, AZWest May 2021target 2025
Onshore wind project 21-08242, Laramie County
Onshore wind
350 MWIn study Laramie, WYWest Aug 2021target 2025
Onshore wind project 408, Wheatland County
Onshore wind
326 MWIn study Wheatland, MTWest Feb 2021target 2024
Onshore wind project C013, Meagher County
Onshore wind
326 MWIn study Meagher, MTWest Jan 2021target 2024
Onshore wind project Q370, Coconino County
Onshore wind
310 MWIn study Coconino, AZWest Mar 2021target 2024
Onshore wind project 407, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Onshore wind project GEN-2021-057, Antelope County
Onshore wind
300 MWIn study Antelope, NESPP Apr 2021target 2027
Pachanga Wind
Onshore wind ยท Pachanga Wind LLC
300 MWIn study Cameron, TXERCOT Feb 2021target 2027
Onshore wind project 406, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Onshore wind project Company LF, Lassen County
Onshore wind
300 MWPaused / redesign Lassen, CAWest Mar 2021target 2023
Onshore wind project Q86, Millard County
Onshore wind ยท Intermountain Power Agency
300 MWIn study Millard, UTWest Nov 2021target 2025
Aquilla Lake 3 Wind
Onshore wind ยท Aquilla Lake 3 Wind
297 MWAgreement signed Hill, TXERCOT Mar 2021target 2027
Onshore wind project BHBE G16, Campbell County
Onshore wind
290 MWAgreement signed Campbell, WYWest Dec 2021target 2024
Yellow Cat Wind
Onshore wind ยท Yellow Cat Wind LLC
262 MWAgreement signed Navarro, TXERCOT Aug 2021target 2027
Onshore wind project J2260, Presque Isle County
Onshore wind
252 MWIn study Presque Isle, MIMISO Oct 2021target 2023
Onshore wind project GEN-2021-016, Johnston County
Onshore wind
250 MWIn study Johnston, OKSPP Apr 2021target 2029
Onshore wind project GEN-2021-069, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2021-068, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Campsey Wind
Onshore wind ยท RWE Clean Energy Development, LLC
238 MWIn study Jack, TXERCOT Feb 2021target 2028
Onshore wind project G0683, Benton County
Onshore wind
233 MWIn study Benton, WAWest Jul 2021target 2026
Onshore wind project GEN-2021-025, Woodward County
Onshore wind
203 MWIn study Woodward, OKSPP May 2021target 2026
Onshore wind project J2080, Oliver County
Onshore wind
200 MWIn study Oliver, NDMISO Aug 2021target 2024
Onshore wind project G0671, Walla Walla County
Onshore wind
200 MWIn study Walla Walla, WAWest Feb 2021target 2025
Onshore wind project J1867, Franklin County
Onshore wind
200 MWIn study Franklin, IAMISO Nov 2021target 2025
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Lane City Wind
Onshore wind ยท RWE Clean Energy, LLC
200 MWAgreement signed Wharton, TXERCOT Apr 2021target 2025
Onshore wind project GI-DISIS-2021-07, Prowers County
Onshore wind
199 MWPaused / redesign Prowers, COWest May 2021target 2026
Onshore wind project J2053, Redwood County
Onshore wind
152 MWIn study Redwood, MNMISO Aug 2021target 2025
Onshore wind project GEN-2021-021, Stevens County
Onshore wind
150 MWIn study Stevens, KSSPP Apr 2021target 2027
Onshore wind project 2021-G6, Yavapai County
Onshore wind
135 MWIn study Yavapai, AZWest Jun 2021target 2025
Onshore wind project J1842, Cross County
Onshore wind
135 MWIn study Cross, ARMISO Oct 2021target 2024
Onshore wind project J2157, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025
Onshore wind project J2031, Tama County
Onshore wind
100 MWIn study Tama, IAMISO Aug 2021target 2026
Onshore wind project J2097, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025
Onshore wind project GI-96, Lincoln County
Onshore wind
97.5 MWAgreement signed Lincoln, OKSoutheast Oct 2021target 2026
Agricola Wind
Onshore wind ยท Agricola Wind LLC
97.0 MWIn study Cayuga, NYNYISO Mar 2021target 2027
Hoffman Falls Wind
Onshore wind ยท Hoffman Falls Wind LLC
72.0 MWIn study Madison, NYNYISO Jan 2021target 2027
Onshore wind project 401, Musselshell County
Onshore wind
70.0 MWIn study Musselshell, MTWest Jan 2021target 2023
Onshore wind project J1998, Franklin County
Onshore wind
66.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Apogee Wind II
Onshore wind ยท King Creek Wind Farm 3, LLC
47.3 MWIn study Throckmorton, TXERCOT Jul 2021target 2027
Onshore wind project J1931, Iowa County
Onshore wind
40.0 MWIn study Iowa, WIMISO Nov 2021target 2025
Onshore wind project GEN-2021-017, Cloud County
Onshore wind
37.5 MWIn study Cloud, KSSPP Apr 2021target 2027
Onshore wind project J2122, Franklin County
Onshore wind
33.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Twin Energy Wind
Onshore wind
18.3 MWAgreement signed Oxford, MEISO-NE Oct 2021target 2026
Onshore wind project J2283, Hillsdale County
Onshore wind
16.1 MWIn study Hillsdale, MIMISO Nov 2021target 2020
Anchor Wind III
Onshore wind ยท RANCHLAND WIND PROJECT LLC
16.0 MWAgreement signed Eastland, TXERCOT Dec 2021target 2025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)