United States › Grid › Interconnection queues › Michigan
ONSHORE WIND · MISOOnshore wind project J2260, Presque Isle County
Onshore wind project J2260, Presque Isle County is a 252 MW onshore wind request in interconnection study in the MISO interconnection queue, in Presque Isle County, Michigan, connecting to METC.
Queue statusIn planning
- PlanningQueued Oct 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2260
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- PORT CALCITE - RIGGSVILLE 138.0kV
- Location
- Presque Isle County, Michigan
- Technology
- Wind: 252 MW
- Total requested
- 252 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 7 October 2021
- Proposed online date
- July 2023
Location
Marker shows the centre of Presque Isle County; the queue data does not give exact sites.
Other requests in Presque Isle County
- Solar project J2875, Presque Isle CountySolar · 150 MW · in study
- Solar project J1914, Presque Isle CountySolar · 150 MW · in study
- Coal project G820, Presque Isle CountyCoal · 600 MW · withdrawn
- Onshore wind project J960, Presque Isle CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J890, Presque Isle CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J296, Presque Isle CountyOnshore wind · 69.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem