🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J2260, Presque Isle County

Onshore wind project J2260, Presque Isle County is a 252 MW onshore wind request in interconnection study in the MISO interconnection queue, in Presque Isle County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Oct 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2260
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
PORT CALCITE - RIGGSVILLE 138.0kV
Location
Presque Isle County, Michigan
Technology
Wind: 252 MW
Total requested
252 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
7 October 2021
Proposed online date
July 2023

Location

Marker shows the centre of Presque Isle County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Presque Isle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem