United States βΊ Grid βΊ Interconnection queues βΊ Michigan
COAL Β· MISOCoal project G820, Presque Isle County
Coal project G820, Presque Isle County is a 600 MW coal request withdrawn in the MISO interconnection queue, in Presque Isle County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2007 (completed)
- Withdrawn / abandonedJan 2012 (project stopped here)
- ConsentedJan 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G820
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Port Calcite - Rockport 138kV
- Location
- Presque Isle County, Michigan
- Technology
- Coal: 600 MW
- Total requested
- 600 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 16 July 2007
- Agreement signed
- 26 January 2012
- Proposed online date
- May 2010
- Withdrawn
- January 2012
Location
Marker shows the centre of Presque Isle County; the queue data does not give exact sites.
Other requests in Presque Isle County
- Onshore wind project J2260, Presque Isle CountyOnshore wind Β· 252 MW Β· in study
- Solar project J2875, Presque Isle CountySolar Β· 150 MW Β· in study
- Solar project J1914, Presque Isle CountySolar Β· 150 MW Β· in study
- Onshore wind project J960, Presque Isle CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project J890, Presque Isle CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project J296, Presque Isle CountyOnshore wind Β· 69.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem