United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6413.6 GW
Active in queue13.6 GW64 requests
Agreement signed9,387 MW47 requests
Withdrawn25952.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

64 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Tehuacana Wind
Onshore wind
600 MWPaused / redesign Limestone, TXERCOT Jun 2017
Onshore wind project G0558, Benton County
Onshore wind
500 MWIn study Benton, WAWest Feb 2017target 2019
Whitehorse Wind
Onshore wind ยท MESQUITE STAR SPECIAL LLC
419 MWAgreement signed Fisher, TXERCOT Jun 20172020
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Mount Laguna Wind 2
Onshore wind
400 MWAgreement signed San Diego, CACAISO May 2017target 2031
Alle Catt II Wind
Onshore wind ยท Alle-Catt Wind Energy LLC
339 MWIn study Cattaraugus, NYNYISO Jan 2017target 2026
Onshore wind project J844, Knox County
Onshore wind
300 MWUnder construction Knox, ILMISO Jun 2017target 2021
Onshore wind project GEN-2017-014, Haakon County
Onshore wind
300 MWAgreement signed Haakon, SDSPP May 2017target 2027
Onshore wind project BHBE G13, Custer County
Onshore wind
300 MWAgreement signed Custer, NEWest Jul 2017target 2023
Onshore wind project GEN-2017-151, Crosby County
Onshore wind
300 MWAgreement signed Crosby, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-181, Lancaster County
Onshore wind
300 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Firelands Wind
Onshore wind
298 MWAgreement signed Erie, OHPJM Mar 2017target 2027
Prairie Hill Wind
Onshore wind ยท Prairie Hill LLC
297 MWAgreement signed Mclennan, TXERCOT Jun 20172020
Onshore wind project GEN-2017-137, Oklahoma County
Onshore wind
295 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project GEN-2017-175, Turner County
Onshore wind
270 MWAgreement signed Turner, SDSPP Nov 2017target 2028
Onshore wind project GEN-2017-158, Parmer County
Onshore wind
265 MWAgreement signed Parmer, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Onshore wind project GEN-2017-149, Johnston County
Onshore wind
258 MWAgreement signed Johnston, OKSPP Nov 2017target 2027
Kontiki 2 Wind (ERNEST)
Onshore wind
250 MWPaused / redesign Glasscock, TXERCOT Jun 2017
Kontiki 1 Wind (ERIK)
Onshore wind
250 MWPaused / redesign Glasscock, TXERCOT Jun 2017
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Onshore wind project G0559, Benton County
Onshore wind
250 MWIn study Benton, WAWest Mar 2017target 2019
Onshore wind project GEN-2017-134, Oklahoma County
Onshore wind
250 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project GEN-2017-201, Wayne County
Onshore wind
250 MWAgreement signed Wayne, NESPP Nov 2017target 2028
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Lutum Wind
Onshore wind ยท RWE
242 MWIn study Clay, TXERCOT Sep 2017target 2027
Giddings Wind
Onshore wind ยท Pioneer Natural Resources
240 MWIn study Upton, TXERCOT Sep 2017target 2030
Monte Cristo 1 Wind
Onshore wind ยท Terra-Gen
235 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2025
Monte Cristo II Wind
Onshore wind ยท Monte Cristo Windpower II, LLC
234 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2028
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Onshore wind project GEN-2017-233, Grady County
Onshore wind
215 MWAgreement signed Grady, OKSPP Nov 2017target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Onshore wind project J722, Codington County
Onshore wind
200 MWUnder construction Codington, SDMISO Jun 2017target 2023
Onshore wind project GEN-2017-144, Holt County
Onshore wind
200 MWAgreement signed Holt, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-133, Oklahoma County
Onshore wind
200 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Wildwind
Onshore wind ยท Wildcat Creek
180 MWAgreement signed Cooke, TXERCOT Oct 20172021
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Onshore wind project GEN-2017-222, Crawford County
Onshore wind
180 MWAgreement signed Crawford, IASPP Nov 2017target 2027
Onshore wind project GI-2017-12, Weld County
Onshore wind
170 MWAgreement signed Weld, COWest Apr 20172020
Onshore wind project GEN-2017-146, Castro County
Onshore wind
152 MWAgreement signed Castro, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Onshore wind project J750, Morgan County
Onshore wind
150 MWUnder construction Morgan, ILMISO Jun 2017target 2022
Onshore wind project 2017-G2
Onshore wind
130 MWIn study West Jan 2017target 2020
Onshore wind project GEN-2017-182, Lancaster County
Onshore wind
128 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-234, Greeley County
Onshore wind
115 MWAgreement signed Greeley, NESPP Nov 20172024
Onshore wind project J855, Grant County
Onshore wind
100 MWUnder construction Grant, WIMISO Jun 20172023
Onshore wind project GEN-2017-215, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)