OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown17532.4 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

175 requests · page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Descendant Ranch 1
Solar + storage
1,024 MWAgreement signed Colusa, CACAISO Apr 2018target 2034
Bellefield Solar Farm
Solar + storage
1,000 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Solar + storage project Q275, Navajo County
Solar + storage
1,000 MWAgreement signed Navajo, AZWest Mar 2018target 2020
Blackwater Solar
Solar
800 MWAgreement signed Sussex, VAPJM Sep 2018target 2029
Centennial Flats
Solar + storage
767 MWAgreement signed La Paz, AZCAISO Apr 2018target 2026
Sanborn Solar 2
Solar + storage
707 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Revoultion Offshore wind
Offshore wind
704 MWAgreement signed RIISO-NE Sep 2018target 2026
Danish Fields Solar
Solar · Danish Fields Solar, LLC
603 MWAgreement signed Wharton, TXERCOT Apr 2018target 2026
Solar project GEN-2018-043, Burt County
Solar
500 MWAgreement signed Burt, NESPP May 2018target 2028
Solar + storage project Company JK, Churchill County
Solar + storage
500 MWAgreement signed Churchill, NVWest Sep 2018target 2027
Siete
Onshore wind · Apex Clean Energy
493 MWAgreement signed Webb, TXERCOT Oct 2018target 2028
Onshore wind project J1026, Audrain County
Onshore wind
400 MWAgreement signed Audrain, MOMISO Mar 2018target 2023
Solar + storage project Company JI, Washoe County
Solar + storage
400 MWAgreement signed Washoe, NVWest Sep 2018target 2023
Solar project Company IF, Humboldt County
Solar
350 MWAgreement signed Humboldt, NVWest Mar 2018target 2026
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Baird North Wind
Onshore wind · BMP Wind, LLC
340 MWAgreement signed Callahan, TXERCOT May 2018target 2026
Quantum Solar
Solar + storage · IP QUANTUM II, LLC
322 MWAgreement signed Haskell, TXERCOT Sep 2018target 2026
Delilah Solar 2
Solar · Delilah Solar Energy II LLC
318 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Key Storage 1
Battery storage
309 MWAgreement signed Fresno, CACAISO Apr 2018target 2026
El Sauz Ranch
Onshore wind · El Sauz Ranch Wind, LLC
302 MWAgreement signed Willacy, TXERCOT Jun 2018target 2026
Pine Forest Solar
Solar · Pine Forest Solar I, LLC
302 MWAgreement signed Hopkins, TXERCOT Oct 2018target 2025
Delilah Solar 1
Solar · Delilah Solar Energy LLC
300 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Solar project GEN-2018-048, Caddo County
Solar
300 MWAgreement signed Caddo, OKSPP May 2018target 2028
Battery storage project Q280, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Sep 2018target 2022
Onshore wind project J982, Dickinson County
Onshore wind
300 MWAgreement signed Dickinson, IAMISO Mar 2018target 2024
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Onshore wind project GEN-2018-099, Parmer County
Onshore wind
300 MWAgreement signed Parmer, TXSPP Nov 2018target 2027
Solar + storage project Company 165, Clark County
Solar + storage
300 MWAgreement signed Clark, NVWest Sep 2018target 2026
Foxtrot Wind
Onshore wind · Lincoln Clean
268 MWAgreement signed Bee, TXERCOT Jul 2018target 2026
Red Holly Solar
Solar + storage · GreenGo Energy
260 MWAgreement signed Dawson, TXERCOT Jul 2018target 2027
Tulsita Solar
Solar · Ray Ranch Solar LLC
256 MWAgreement signed Goliad, TXERCOT Dec 2018target 2026
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Maleza Solar
Solar + storage · Brush Solar LLC
255 MWAgreement signed Wharton, TXERCOT Dec 2018target 2027
Roseland Solar
Solar · Enel Green Power Roseland Solar, LLC
254 MWAgreement signed Falls, TXERCOT Nov 2018target 2025
Onshore wind project 2019-G2
Onshore wind
252 MWAgreement signed West Nov 2018target 2022
Solar project GEN-2018-055, Grady County
Solar
252 MWAgreement signed Grady, OKSPP May 2018target 2026
Onshore wind project 2019-G1
Onshore wind
252 MWAgreement signed West Nov 2018target 2021
Solar project GEN-2018-015, Cottle County
Solar
252 MWAgreement signed Cottle, TXSPP Apr 2018target 2027
Adamstown Solar
Solar · Adams Creek Solar Project, LLC
251 MWAgreement signed Wichita, TXERCOT Nov 2018target 2027
Solar + storage project GI-2018-24, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Aug 20182022
Solar project IC-695, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project J1145, Callaway County
Solar
250 MWAgreement signed Callaway, MOMISO Mar 2018target 2024
Samson Solar 1
Solar · Samson Solar Energy LLC
250 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Solar + storage project GEN-2018-115, Comanche County
Solar + storage
250 MWAgreement signed Comanche, OKSPP Nov 2018target 2029
Solar project IC-696, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Eastbell Milam Solar
Solar · EDP RENEWABLES NORTH AMERICA LLC
245 MWAgreement signed Milam, TXERCOT Oct 2018target 2025
Peyton Creek Wind II
Onshore wind · RWE Renewables Development, LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2018target 2026
Cadence Solar Energy Center
Solar
240 MWAgreement signed Union, OHPJM Mar 2018target 2026
Onshore wind project GEN-2018-125, Lancaster County
Onshore wind
231 MWAgreement signed Lancaster, NESPP Nov 2018target 2031
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)