United States โบ Grid โบ Interconnection queues โบ Texas
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Texas (2023 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project GEN-2023-240, Bailey County Solar |
550 MW | Withdrawn / abandoned |
| Apis Solar Solar ยท S&S Renewables LLC |
534 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-237, Hale County Onshore wind |
500 MW | Withdrawn / abandoned |
| Upstream BESS Battery storage ยท Upstream Storage LLC |
462 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2023-212, Bowie County Solar + storage |
400 MW | Withdrawn / abandoned |
| Bedias Solar Park Solar ยท Misae Energy III |
400 MW | Withdrawn / abandoned |
| Other project GEN-2022-112, Hansford County Other |
370 MW | Withdrawn / abandoned |
| Solar project GEN-2022-221, Wilbarger County Solar |
350 MW | Withdrawn / abandoned |
| Umbra Solar II Solar ยท Saddle House Solar Project, LLC |
345 MW | Withdrawn / abandoned |
| Solar project GEN-2023-158, Bailey County Solar |
335 MW | Withdrawn / abandoned |
| Valhalla Solar Solar ยท Industrial Papa Project LLC |
307 MW | Withdrawn / abandoned |
| Fox Run Energy Storage Other ยท Fox Run Energy Project, LLC |
301 MW | Withdrawn / abandoned |
| Blossomheath BESS Battery storage ยท Taurbeng LLC |
301 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-199, Castro County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-201, Lamb County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2023-239, Potter County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project GEN-2024-SR4, Yoakum County Battery storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2023-086, Randall County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-176, Lamb County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2022-236, Lamb County Solar |
299 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-123, Ochiltree County Onshore wind |
285 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-010, Sherman County Onshore wind |
280 MW | Withdrawn / abandoned |
| Solar project GEN-2023-238, Potter County Solar |
280 MW | Withdrawn / abandoned |
| Solar project GEN-2023-142, Lamb County Solar |
275 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-217, Parmer County Onshore wind |
275 MW | Withdrawn / abandoned |
| Apis Storage Battery storage ยท S&S Renewables LLC |
268 MW | Withdrawn / abandoned |
| OCI SunRoper ESS Other ยท OCI SunRoper LLC |
266 MW | Withdrawn / abandoned |
| Emerald Hill Energy Storage Battery storage ยท Emerald Hill Energy Storage LLC |
261 MW | Withdrawn / abandoned |
| Solar project GEN-2023-060, Lamb County Solar |
256 MW | Withdrawn / abandoned |
| Solar project GEN-2023-005, Lamb County Solar |
256 MW | Withdrawn / abandoned |
| Battery storage project GEN-2022-133, Potter County Battery storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-216, Castro County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-122, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-121, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Battery storage project GEN-2023-228, Cottle County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-127, Lamb County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-118, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-120, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-116, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-126, Lamb County Solar |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-110, Hall County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-125, Ochiltree County Onshore wind |
250 MW | Withdrawn / abandoned |
| Battery storage project GEN-2022-242, Wilbarger County Battery storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-117, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-128, Lamb County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-127, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-129, Lamb County Solar |
250 MW | Withdrawn / abandoned |
| Battery storage project GEN-2022-141, Lubbock County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2023-195, Bailey County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-119, Oldham County Onshore wind |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)