ONSHORE WIND Β· SPP

Onshore wind project GEN-2022-199, Castro County

Onshore wind project GEN-2022-199, Castro County is a 300 MW onshore wind request withdrawn in the SPP interconnection queue, in Castro County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-199
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Newhart 230kV Substation
Location
Castro County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 February 2023
Proposed online date
December 2027
Withdrawn
November 2023

Location

Marker shows the centre of Castro County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Castro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem