ONSHORE WIND Β· SPPOnshore wind project GEN-2022-122, Oldham County
Onshore wind project GEN-2022-122, Oldham County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Oldham County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-122
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Potter 345kV Substation
- Location
- Oldham County, Texas
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 16 February 2023
- Proposed online date
- December 2027
- Withdrawn
- November 2023
Location
Marker shows the centre of Oldham County; the queue data does not give exact sites.
Other requests in Oldham County
- Channing WindOnshore wind Β· 361 MW Β· suspended
- Onshore wind project GEN-2002-022, Oldham CountyOnshore wind Β· 239 MW Β· built
- Canadian Breaks WindOnshore wind Β· 210 MW Β· built
- Onshore wind project GEN-2008-051, Oldham CountyOnshore wind Β· 161 MW Β· built
- Onshore wind project GEN-2008-084, Oldham CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2022-121, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-118, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-120, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-116, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-117, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-127, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-119, Oldham CountyOnshore wind Β· 250 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem