ONSHORE WIND · SPPOnshore wind project GEN-2002-022, Oldham County
Onshore wind project GEN-2002-022, Oldham County is a 239 MW onshore wind request built and operating in the SPP interconnection queue, in Oldham County, Texas, connecting to SPS.
Request details
- Queue ID
- GEN-2002-022
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Bushland 230kV
- Location
- Oldham County, Texas
- Technology
- Wind: 239 MW
- Total requested
- 239 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 12 September 2002
- Proposed online date
- December 2006
- Came online
- December 2006
Location
Marker shows the centre of Oldham County; the queue data does not give exact sites.
Other requests in Oldham County
- Channing WindOnshore wind · 361 MW · suspended
- Canadian Breaks WindOnshore wind · 210 MW · built
- Onshore wind project GEN-2008-051, Oldham CountyOnshore wind · 161 MW · built
- Onshore wind project GEN-2008-084, Oldham CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2022-122, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-121, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-118, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-120, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-116, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-117, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-127, Oldham CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-119, Oldham CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem