πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2008-084, Oldham County

Onshore wind project GEN-2008-084, Oldham County is a 300 MW onshore wind request withdrawn in the SPP interconnection queue, in Oldham County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2008-084
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Location
Oldham County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 August 2008
Proposed online date
June 2011

Location

Marker shows the centre of Oldham County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Oldham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem