ONSHORE WIND Β· SPP

Onshore wind project GEN-2023-010, Sherman County

Onshore wind project GEN-2023-010, Sherman County is a 280 MW onshore wind request withdrawn in the SPP interconnection queue, in Sherman County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-010
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Moore Co 230 kV Substation
Location
Sherman County, Texas
Technology
Wind: 280 MW
Total requested
280 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
December 2030
Withdrawn
August 2025

Location

Marker shows the centre of Sherman County; the queue data does not give exact sites.