πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2011-012, Sherman County

Onshore wind project GEN-2011-012, Sherman County is a 105 MW onshore wind request withdrawn in the SPP interconnection queue, in Sherman County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedSep 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2011-012
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Moore County - Hitchland 345kV
Location
Sherman County, Texas
Technology
Wind: 105 MW
Total requested
105 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2012
Withdrawn
September 2013

Location

Marker shows the centre of Sherman County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Sherman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem