United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Texas (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26154.0 GW
Active in queue79.0 GW369 requests
Agreement signed25.0 GW108 requests
Withdrawn11324.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

261 requests · page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Hecate Energy Orem Wind
Onshore wind · Hecate Energy LLC
1,542 MWIn study Brazoria, TXERCOT Jun 2023target 2030
Hecate Energy Arkansas Wind
Onshore wind · Hecate Energy Gulf Wind LLC
1,029 MWIn study San Patricio, TXERCOT Jun 2023target 2030
Hecate Energy Jamaica Wind
Onshore wind · Hecate Energy LLC
1,029 MWIn study Galveston, TXERCOT Jun 2023target 2030
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Jack County III – 345 kV
Gas · Jack County Power Development, LLC
660 MWIn study Jack, TXERCOT Nov 2023target 2027
Aurelius 3 Wind
Onshore wind · IP Roman III, LLC
623 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Aurelius 2 Wind
Onshore wind · IP Roman Wind II, LLC
622 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Tumbleweed Solar
Solar + storage · Hecate Energy Tumbleweed Solar LLC
614 MWIn study Borden, TXERCOT Sep 2023target 2027
White Oak King Wind
Onshore wind · KSK Wind Farm 1, LLC
607 MWIn study King, TXERCOT Mar 2023target 2027
Rocking X Solar
Solar · 7100 Tin Top LLC
602 MWIn study Parker, TXERCOT Oct 2023target 2027
Longleaf Power Station
Gas · WattBridge Texas Holding, LLC
600 MWIn study Angelina, TXERCOT Oct 2023target 2028
Crescent C BESS
Battery storage · OCI La Salle ESS LLC
508 MWIn study La Salle, TXERCOT Apr 2023target 2028
Tumbleweed Storage
Solar + storage · Hecate Energy Tumbleweed Storage LLC
507 MWIn study Borden, TXERCOT Oct 2023target 2027
Oriole Solar
Solar + storage · Rolling Plains Solar
504 MWIn study Knox, TXERCOT May 2023target 2028
Freedom Falcon BESS
Battery storage · Falcon BESS, LLC
502 MWIn study Zapata, TXERCOT Jun 2023target 2028
Titus Sienta Solar
Solar · Sol Sienta Solar, LLC
502 MWIn study Pecos, TXERCOT Oct 2023target 2028
Orbit Energy Storage
Battery storage · GCI Orbit Energy Storage, LLC
502 MWIn study Bexar, TXERCOT Nov 2023target 2027
Salt-Lick Solar
Solar + storage · Salt-Lick Solar, LLC
453 MWIn study Culberson, TXERCOT Oct 2023target 2028
TRIFECTA Gas
Gas · NET Power
453 MWIn study Midland, TXERCOT Jun 2023target 2030
Aurelius 2 Solar
Solar · IP Roman, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Aurelius 3 Solar
Solar · IP Roman III, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Western Flats Solar
Solar + storage · Hecate Energy Point Mountain Solar Facility 1 LLC
410 MWIn study Crane, TXERCOT Apr 2023target 2028
Silverton Solar
Solar · NextEra Energy Interconnection Holdings, LLC
410 MWIn study Briscoe, TXERCOT Dec 2023target 2029
Lund Storage Center 1
Battery storage · Lund Storage Center 1, LLC
408 MWIn study Bastrop, TXERCOT Jan 2023target 2026
Claire BESS
Battery storage · BRP Blue Topaz 3, LLC
406 MWIn study Harris, TXERCOT Feb 2023target 2027
Boling Generation (TEF-Due Diligience)
Gas · Boling Generation
400 MWIn study Wharton, TXERCOT Dec 2023target 2027
Scott Crossing Solar SLF
Solar + storage · FRESH AIR ENERGY II, LLC
364 MWIn study Haskell, TXERCOT Mar 2023target 2027
Channing Wind
Onshore wind
361 MWPaused / redesign Oldham, TXERCOT Dec 2023target 2028
Tetris Solar
Solar · NextEra Energy Interconnection Holdings LLC
359 MWIn study Zapata, TXERCOT Jul 2023target 2029
Tetris Solar (Alternative POI)
Solar
359 MWPaused / redesign Zapata, TXERCOT Jul 2023target 2028
Funston Solar (AEP POI)
Solar
355 MWPaused / redesign Jones, TXERCOT Sep 2023target 2028
Titus Low Carbon Ventures Solar 1
Solar · Vaquero Solar, LLC
338 MWIn study San Patricio, TXERCOT Oct 2023target 2028
Bulldog Power (TEF - Due Diligence)
Gas · Bulldog Power LLC
311 MWIn study Brazoria, TXERCOT Nov 2023target 2027
Oak Tree Energy Storage
Battery storage · Live Oak Energy Storage, LLC
310 MWIn study Lavaca, TXERCOT Dec 2023target 2029
Buffalo Prairie Storage
Solar + storage · Buffalo Meadow Energy Center, LLC
308 MWIn study Robertson, TXERCOT Jan 2023target 2028
Haute Stockage
Battery storage
307 MWPaused / redesign Shackelford, TXERCOT Oct 2023target 2027
Beaujolais BESS
Battery storage
307 MWPaused / redesign Lamar, TXERCOT Dec 2023target 2026
Cuchillas BESS
Solar + storage · Gransolar Texas Two
307 MWIn study Webb, TXERCOT Sep 2023target 2028
Wolf Hollow III
Gas · Wolf Hollow II Power LLC
306 MWIn study Hood, TXERCOT Jun 2023target 2027
WOE Gyp King Wind
Onshore wind · KSK Wind Farm 1, LLC
304 MWPaused / redesign King, TXERCOT Apr 2023target 2029
Whitewright Solar 2
Solar · SunWR, LLC
302 MWIn study Grayson, TXERCOT Dec 2023target 2028
Amerada Solar
Solar + storage · Amerada Solar, LLC
302 MWIn study Freestone, TXERCOT May 2023target 2028
Riverbend Solar SLF
Solar + storage · Riverbend Renewables, LLC
302 MWIn study Falls, TXERCOT Mar 2023target 2027
Rubicon Power BESS
Battery storage · Rubicon Power LLC
301 MWIn study Brazoria, TXERCOT Nov 2023target 2026
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Tres Rios Ranch BESS
Solar + storage · LectricWind LLC
290 MWIn study Upton, TXERCOT May 2023target 2027
Inadale BESS
Solar + storage · Inadale BESS, LLC
287 MWIn study Scurry, TXERCOT Feb 2023target 2028
Inadale Solar
Solar + storage · Inadale Solar, LLC
281 MWIn study Scurry, TXERCOT Feb 2023target 2028
Santa Garcias Solar
Solar · Oxy Renewable Energy LLC
265 MWIn study Kleberg, TXERCOT Jun 2023target 2028
Ochoa Energy Storage
Battery storage · Ochoa Energy Storage LLC
260 MWIn study Waller, TXERCOT Apr 2023target 2027
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)