United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in Texas (2022 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Meitner Solar Solar · IP Meitner, LLC |
703 MW | Agreement signed |
| Short Creek Solar Solar + storage · Wichita Solar I, LLC |
628 MW | Agreement signed |
| Gas project GEN-2022-GR1, Harrison County Gas |
513 MW | Agreement signed |
| Midnight Sun Energy Storage Battery storage · Midnight Sun Energy Storage, LLC |
510 MW | Agreement signed |
| Austin Bayou Solar Solar + storage · Austin Bayou Solar, LLC |
503 MW | Agreement signed |
| Hollow Branch Creek Solar Solar + storage · Hollow Branch Creek Solar LLC |
460 MW | Agreement signed |
| NRG THW GT 345 (Tef) Gas · NRG THW GT LLC |
456 MW | Agreement signed |
| Soleil Solar Solar · Soleil Solar, LLC |
452 MW | Agreement signed |
| Zeissel Solar Solar · ZSS Power, LLC |
452 MW | Agreement signed |
| NRG Greens Bayou 6 (TEF-Due Diligence) Gas · NRG Greens Bayou 6 LLC |
445 MW | Agreement signed |
| Bug Tussle Wind Project Onshore wind · Bug Tussle Wind, LLC |
397 MW | Agreement signed |
| Rowdy Creek Solar Solar + storage · Rowdy Creek Solar LLC |
352 MW | Agreement signed |
| Elio BESS Battery storage · Elio Energy LLC |
317 MW | Agreement signed |
| Middlebrook Solar Limited Liability Company Solar + storage · Middlebrook Solar LLC |
316 MW | Agreement signed |
| Red Egret BESS Battery storage · Red Egret LLC |
311 MW | Agreement signed |
| Argenta Solar Solar + storage · Charter Oak Solar, LLC |
310 MW | Agreement signed |
| Two Forks BESS Battery storage · Two Forks LLC |
310 MW | Agreement signed |
| SanPat Solar I Solar · Padre Solar LLC |
309 MW | Agreement signed |
| Blue Skies BESS Battery storage · ACTX BESS Project LLC |
306 MW | Agreement signed |
| Great Rock BESS Battery storage · Black Mountain Energy Storage II |
301 MW | Agreement signed |
| Piedra Solar Solar + storage · Piedra Solar, LLC |
282 MW | Agreement signed |
| Crossroads Wind Onshore wind · HyFuels Green Lake Wind LLC |
277 MW | Agreement signed |
| Mystic Springs Renewable Energy Solar SLF Solar + storage · Mystic Spring Renewable Energy LLC |
259 MW | Agreement signed |
| Drake BESS Battery storage · Mallard Energy Storage LLC |
257 MW | Agreement signed |
| Shepard Energy Storage Battery storage · Shepard Energy Storage LLC |
257 MW | Agreement signed |
| SanPat Solar II Solar · CGRP 04, LLC |
256 MW | Agreement signed |
| Cibeles Solar Solar · Elawan Cibeles Solar, LLC |
252 MW | Agreement signed |
| Buzios Solar Solar + storage · Roaring Springs Solar, LLC |
252 MW | Agreement signed |
| August Draw Solar Solar · August Draw Solar Holdings, LLC |
250 MW | Agreement signed |
| Bracero Pecan Storage Battery storage · Bracero Pecan Storage LLC |
238 MW | Agreement signed |
| Taormina Storage Battery storage · Taormina Storage Project LLC |
232 MW | Agreement signed |
| Adelite Storage Battery storage · Adelite Storage Project LLC |
232 MW | Agreement signed |
| Lavender Storage Project Battery storage · Lavender Storage Project LLC |
232 MW | Agreement signed |
| Diver Solar Solar · Diver Solar |
226 MW | Agreement signed |
| Rubicon Alpha Wind Onshore wind · Throckmorton Wind, LLC |
226 MW | Agreement signed |
| Rockridge Solar Solar · Magnolia Solar Development LLC |
211 MW | Agreement signed |
| Cumulus Grid BESS Battery storage · Cumulus Grid, LLC |
211 MW | Agreement signed |
| Leon Solar Park Solar + storage · Misae Solar IV LLC |
210 MW | Agreement signed |
| Anatole Renewable Energy Storage Battery storage · Eustace Storage LLC |
208 MW | Agreement signed |
| Longfellow Solar II Solar + storage · CENTURY GAS PROCESSING, LLC |
207 MW | Agreement signed |
| Pintail Pass BESS Battery storage · Pintail Pass BESS, LLC |
207 MW | Agreement signed |
| Rhapsody Storage Battery storage · Destiny Storage, LLC |
206 MW | Agreement signed |
| Sahara II BESS (Soho II BESS) Battery storage · ESTX-PLD-HOUSTON2 |
204 MW | Agreement signed |
| Soda Lake BESS 1 Battery storage · Mendoza Trail BESS, LLC |
204 MW | Agreement signed |
| Black & Gold Energy Storage Battery storage · Black & Gold Energy Storage, LLC |
204 MW | Agreement signed |
| Glasgow Solar Solar + storage · Glasgow Solar LLC |
204 MW | Agreement signed |
| OCI Cobb Creek Solar Solar + storage · Hillsboro Solar Project LLC |
203 MW | Agreement signed |
| Wolf Spring Storage Solar + storage · Wolf Spring Solar, LLC |
203 MW | Agreement signed |
| Goldeneye BESS Battery storage · Black Mountain Energy Storage II |
202 MW | Agreement signed |
| OCI Cobb Creek ESS Solar + storage · Hillsboro Solar Project LLC |
202 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)