πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Ohio (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown443,624 MW
Active in queue3,624 MW44 requests
Agreement signed0.0 MW0 requests
Withdrawn242,330 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AI1-167, Clermont County
Battery storage
250 MWIn study Clermont, OHPJM Sep 2022target 2028
Solar project AI1-103, Champaign County
Solar
200 MWIn study Champaign, OHPJM Aug 2022target 2029
Onshore wind project AI1-168, Coshocton County
Onshore wind
200 MWIn study Coshocton, OHPJM Sep 2022target 2027
Solar project AH2-168, Madison County
Solar
185 MWIn study Madison, OHPJM Mar 2022target 2025
Solar project AI2-028, Union County
Solar
160 MWIn study Union, OHPJM Dec 2022target 2026
Solar + storage project AI1-100, Belmont County
Solar + storage
150 MWIn study Belmont, OHPJM Aug 2022target 2025
Battery storage project AH2-228, Pickaway County
Battery storage
150 MWIn study Pickaway, OHPJM Mar 2022target 2026
Solar + storage project AI1-074, Jackson County
Solar + storage
120 MWIn study Jackson, OHPJM Jul 2022target 2027
Solar project AH2-345, Lorain County
Solar
120 MWIn study Lorain, OHPJM Mar 2022target 2025
Solar project AH2-264, Van Wert County
Solar
115 MWIn study Van Wert, OHPJM Mar 2022target 2026
Battery storage project AH2-126, Jefferson County
Battery storage
100 MWIn study Jefferson, OHPJM Feb 2022target 2026
Solar + storage project AI1-190, Union County
Solar + storage
100 MWIn study Union, OHPJM Sep 2022target 2027
Solar project AH2-068, Wood County
Solar
100 MWIn study Wood, OHPJM Jan 2022target 2027
Battery storage project AH2-217, Morrow County
Battery storage
100 MWIn study Morrow, OHPJM Mar 2022target 2026
Solar project AH2-155, Fulton County
Solar
95.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Solar + storage project AH2-146, Adams County
Solar + storage
87.2 MWIn study Adams, OHPJM Feb 2022target 2027
Solar + storage project AI1-112, Champaign County
Solar + storage
85.0 MWIn study Champaign, OHPJM Aug 2022target 2026
Solar project AH2-164, Crawford County
Solar
85.0 MWIn study Crawford, OHPJM Mar 2022target 2026
Battery storage project AH2-374, Richland County
Battery storage
84.0 MWIn study Richland, OHPJM Mar 2022target 2027
Solar project AH2-165, Fulton County
Solar
80.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Solar project AH2-169, Perry County
Solar
80.0 MWIn study Perry, OHPJM Mar 2022target 2025
Solar project AI2-029, Union County
Solar
70.0 MWIn study Union, OHPJM Dec 2022target 2026
Gas project AH2-106, Columbiana County
Gas
69.0 MWIn study Columbiana, OHPJM Feb 2022target 2022
Solar project AI2-024, Meigs County
Solar
60.0 MWIn study Meigs, OHPJM Dec 2022target 2028
Solar project AI1-151, Adams County
Solar
53.2 MWIn study Adams, OHPJM Sep 2022target 2027
Solar + storage project AH2-408, Wood County
Solar + storage
49.9 MWIn study Wood, OHPJM Mar 2022target 2025
Solar project AI1-091, Seneca County
Solar
49.9 MWIn study Seneca, OHPJM Aug 2022target 2025
Solar project AI1-092, Butler County
Solar
49.9 MWIn study Butler, OHPJM Aug 2022target 2025
Solar + storage project AI1-150, Butler County
Solar + storage
49.9 MWIn study Butler, OHPJM Sep 2022target 2027
Solar project AH2-159, Highland County
Solar
49.0 MWIn study Highland, OHPJM Mar 2022target 2025
Solar + storage project AH2-239, Trumbull County
Solar + storage
49.0 MWIn study Trumbull, OHPJM Mar 2022target 2027
Solar + storage project AH2-346, Hancock County
Solar + storage
47.5 MWIn study Hancock, OHPJM Mar 2022target 2025
Solar + storage project AH2-242, Montgomery County
Solar + storage
45.0 MWIn study Montgomery, OHPJM Mar 2022target 2027
Solar + storage project AH2-344, Marion County
Solar + storage
45.0 MWIn study Marion, OHPJM Mar 2022target 2025
Solar project AH2-166, Fulton County
Solar
45.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Solar project AH2-156, Huron County
Solar
40.0 MWIn study Huron, OHPJM Mar 2022target 2025
Solar project AH2-081, Fayette County
Solar
35.5 MWIn study Fayette, OHPJM Jan 2022target 2025
Solar project AH2-082, Fayette County
Solar
33.3 MWIn study Fayette, OHPJM Jan 2022target 2025
Solar + storage project AH2-093, Greene County
Solar + storage
32.0 MWIn study Greene, OHPJM Jan 2022target 2025
Solar + storage project AH2-409, Wood County
Solar + storage
30.1 MWIn study Wood, OHPJM Mar 2022target 2025
Solar project AH2-160, Highland County
Solar
20.0 MWIn study Highland, OHPJM Mar 2022target 2025
Gas project AH2-111, Monroe County
Gas
20.0 MWIn study Monroe, OHPJM Feb 2022target 2022
Solar + storage project AI1-175, Marion County
Solar + storage
19.5 MWIn study Marion, OHPJM Sep 2022target 2024
Solar project AI1-139, Lorain County
Solar
14.8 MWIn study Lorain, OHPJM Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)