Requests shown337,254 MW
Active in queue7,254 MW33 requests
Agreement signed0.0 MW0 requests
Withdrawn244,594 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

33 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Surplus; Big Bend
Wind + storage
550 MWIn study Cottonwood, MNMISO Jul 2024target 2027
Solar project J3532, Roseau County
Solar
500 MWIn study Roseau, MNMISO Apr 2024target 2028
Solar project J3762, Clay County
Solar
430 MWIn study Clay, MNMISO Apr 2024target 2028
Solar project J3399, Goodhue County
Solar
300 MWIn study Goodhue, MNMISO Apr 2024target 2028
Onshore wind project J3384, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Onshore wind project J3672, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Solar project J3669, Stevens County
Solar
300 MWIn study Stevens, MNMISO Apr 2024target 2028
Onshore wind project J3326, Lyon County
Onshore wind
250 MWIn study Lyon, MNMISO Apr 2024target 2028
Battery storage project J3848, Wabasha County
Battery storage
250 MWIn study Wabasha, MNMISO Dec 2024target 2030
Wind + storage project J3443, Big Stone County
Wind + storage
250 MWIn study Big Stone, MNMISO Apr 2024target 2028
Battery storage project J3235, Benton County
Battery storage
250 MWIn study Benton, MNMISO Mar 2024target 2028
Onshore wind project J3275, Benton County
Onshore wind
249 MWIn study Benton, MNMISO Apr 2024target 2028
Replacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4
Gas
237 MWIn study Chippewa, MNMISO Mar 2024target 2025
Gas project J3289, Sherburne County
Gas
235 MWIn study Sherburne, MNMISO Apr 2024target 2026
Gas project J3465, Isanti County
Gas
211 MWIn study Isanti, MNMISO Mar 2024target 2026
Solar project J1581, Nobles County
Solar
200 MWIn study Nobles, MNMISO Apr 2024target 2026
Battery storage project J3704, Redwood County
Battery storage
200 MWIn study Redwood, MNMISO Apr 2024target 2028
Solar project J3434, Kandiyohi County
Solar
200 MWIn study Kandiyohi, MNMISO Mar 2024target 2028
Battery storage project J3236, Chisago County
Battery storage
200 MWIn study Chisago, MNMISO Mar 2024target 2028
Battery storage project J3703, Itasca County
Battery storage
200 MWIn study Itasca, MNMISO Mar 2024target 2028
Onshore wind project J3749, Lyon County
Onshore wind
200 MWIn study Lyon, MNMISO Apr 2024target 2028
Solar + storage project J3742, Otter Tail County
Solar + storage
160 MWIn study Otter Tail, MNMISO Jun 2024target 2028
Battery storage project J3543, Dakota County
Battery storage
150 MWIn study Dakota, MNMISO Apr 2024target 2028
Solar project J3051, Chisago County
Solar
150 MWIn study Chisago, MNMISO Jan 2024target 2026
Solar project J3850, Pine County
Solar
150 MWIn study Pine, MNMISO Dec 2024target 2030
Solar project J3233, Yellow Medicine County
Solar
140 MWIn study Yellow Medicine, MNMISO Mar 2024target 2028
Replacing 135.5 MW with 135.5 MW BESS; Blue Lake Units 1 2 4
Other
136 MWIn study Scott, MNMISO May 2024target 2027
Solar project J1620, Pipestone County
Solar
125 MWIn study Pipestone, MNMISO Apr 2024target 2026
Solar project J3552, Mcleod County
Solar
112 MWIn study Mcleod, MNMISO Apr 2024target 2028
Solar project J3439, Sherburne County
Solar
100 MWIn study Sherburne, MNMISO Apr 2024target 2026
Surplus; J385
Other
100 MWIn study Chisago, MNMISO Jul 2024target 2026
Solar project J3529, Mahnomen County
Solar
64.0 MWIn study Mahnomen, MNMISO May 2024target 2028
Replacing 55 MW with 29 MW Natural Gas/Fuel Oil; Blue Lake Unit 3
Gas
55.0 MWIn study Scott, MNMISO May 2024target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)