United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J3233, Yellow Medicine County

Solar project J3233, Yellow Medicine County is a 140 MW solar request in interconnection study in the MISO interconnection queue, in Yellow Medicine County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3233
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Canby 115 kV Substation
Location
Yellow Medicine County, Minnesota
Technology
Solar: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
28 March 2024
Proposed online date
January 2028

Location

Marker shows the centre of Yellow Medicine County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Yellow Medicine County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem