πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G823, Yellow Medicine County

Onshore wind project G823, Yellow Medicine County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Yellow Medicine County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. ConsentedJun 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G823
Grid region
MISO (Midcontinent)
Connection point (POI)
Burr - Toronto 115 kV
Location
Yellow Medicine County, Minnesota
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
24 July 2007
Agreement signed
19 June 2012
Proposed online date
December 2009
Withdrawn
June 2012

Location

Marker shows the centre of Yellow Medicine County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Yellow Medicine County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem