United States › Grid › Interconnection queues › Minnesota

BATTERY STORAGE · MISO

Battery storage project J3703, Itasca County

Battery storage project J3703, Itasca County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Itasca County, Minnesota, connecting to MINNESOTA POWER INC..

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3703
Grid region
MISO (Midcontinent)
Utility / transmission owner
MINNESOTA POWER INC.
Connection point (POI)
Blackberry 230/115kV
Location
Itasca County, Minnesota
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
25 March 2024
Proposed online date
June 2028

Location

Marker shows the centre of Itasca County; the queue data does not give exact sites.