πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Louisiana (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown425,320 MW
Active in queue2,108 MW14 requests
Agreement signed305 MW4 requests
Withdrawn425,320 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

42 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2176, Calcasieu Parish County
Solar
680 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Aug 2021target 2025
Solar project J2310, Beauregard Parish County
Solar
300 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2021target 2024
Solar + storage project J2020, Beauregard Parish County
Solar + storage
260 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Solar project J1868, Winn Parish County
Solar
260 MWWithdrawn / abandoned Winn Parish, LAMISO Aug 2021target 2024
Solar project J2183, Pointe Coupee Parish County
Solar
200 MWWithdrawn / abandoned Pointe Coupee Parish, LAMISO Sep 2021target 2022
Solar project J2083, Allen Parish County
Solar
200 MWWithdrawn / abandoned Allen Parish, LAMISO Dec 2021target 2024
Solar project J2135, Evangeline Parish County
Solar
200 MWWithdrawn / abandoned Evangeline Parish, LAMISO Aug 2021target 2024
Solar project J2167, Calcasieu Parish County
Solar
198 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Nov 2021target 2023
Solar project J1995, Richland Parish County
Solar
180 MWWithdrawn / abandoned Richland Parish, LAMISO Aug 2021target 2025
Solar project J2096, Terrebonne Parish County
Solar
180 MWWithdrawn / abandoned Terrebonne Parish, LAMISO Aug 2021target 2024
Solar project J2077, Livingston Parish County
Solar
150 MWWithdrawn / abandoned Livingston Parish, LAMISO Dec 2021target 2024
Solar + storage project J2154, Calcasieu Parish County
Solar + storage
150 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Aug 2021target 2024
Battery storage project J2210, Iberville Parish County
Battery storage
100 MWWithdrawn / abandoned Iberville Parish, LAMISO Aug 2021target 2025
Battery storage project J2222, Calcasieu Parish County
Battery storage
100 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Dec 2021target 2024
Solar project J1850, St. Martin Parish County
Solar
100 MWWithdrawn / abandoned St. Martin Parish, LAMISO Nov 2021target 2024
Battery storage project J1908, Evangeline Parish County
Battery storage
100 MWWithdrawn / abandoned Evangeline Parish, LAMISO Aug 2021target 2022
Solar + storage project GEN-2021-104, Bossier Parish County
Solar + storage
100 MWWithdrawn / abandoned Bossier Parish, LASPP May 2021target 2027
Solar project J1959, St. John The Baptist Parish County
Solar
100 MWWithdrawn / abandoned St. John The Baptist Parish, LAMISO Nov 2021target 2025
Solar + storage project J2245, St. Tammany Parish County
Solar + storage
100 MWWithdrawn / abandoned St. Tammany Parish, LAMISO Aug 2021target 2024
Battery storage project J2202, Jefferson Davis Parish County
Battery storage
100 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Aug 2021target 2022
Battery storage project J1906, Washington Parish County
Battery storage
100 MWWithdrawn / abandoned Washington Parish, LAMISO Aug 2021target 2022
Solar project J1999, Rapides Parish County
Solar
100 MWWithdrawn / abandoned Rapides Parish, LAMISO Dec 2021target 2024
Solar project J2191, St. Mary Parish County
Solar
100 MWWithdrawn / abandoned St. Mary Parish, LAMISO Oct 2021target 2025
Solar project J1933, Morehouse Parish County
Solar
100 MWWithdrawn / abandoned Morehouse Parish, LAMISO Aug 2021target 2025
Solar project J1883, Ouachita Parish County
Solar
100 MWWithdrawn / abandoned Ouachita Parish, LAMISO Jul 2021target 2023
Solar project J2169, Beauregard Parish County
Solar
98.9 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2023
Solar project J2025, St. James Parish County
Solar
95.0 MWWithdrawn / abandoned St. James Parish, LAMISO Aug 2021target 2025
Solar project J1887, St. Martin Parish County
Solar
90.0 MWWithdrawn / abandoned St. Martin Parish, LAMISO Aug 2021target 2024
Solar project J2257, Evangeline Parish County
Solar
80.0 MWWithdrawn / abandoned Evangeline Parish, LAMISO Aug 2021target 2024
Solar project J1997, Beauregard Parish County
Solar
80.0 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Battery storage project J1869, Winn Parish County
Battery storage
78.0 MWWithdrawn / abandoned Winn Parish, LAMISO Aug 2021target 2024
Battery storage project J2214, Sabine Parish County
Battery storage
62.0 MWWithdrawn / abandoned Sabine Parish, LAMISO Dec 2021target 2024
Battery storage project J1956, St. John The Baptist Parish County
Battery storage
60.0 MWWithdrawn / abandoned St. John The Baptist Parish, LAMISO Nov 2021target 2025
Battery storage project J1871, Tangipahoa Parish County
Battery storage
60.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Aug 2021target 2024
Battery storage project J1958, St. John The Baptist Parish County
Battery storage
60.0 MWWithdrawn / abandoned St. John The Baptist Parish, LAMISO Nov 2021target 2025
Battery storage project J2013, Tangipahoa Parish County
Battery storage
52.9 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Nov 2021target 2025
Battery storage project J2011, Morehouse Parish County
Battery storage
50.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO Aug 2021target 2025
Solar project J1985, Tangipahoa Parish County
Solar
50.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Nov 2021target 2025
Battery storage project J2220, Iberville Parish County
Battery storage
50.0 MWWithdrawn / abandoned Iberville Parish, LAMISO Dec 2021target 2024
Solar project J2082, Rapides Parish County
Solar
50.0 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2021target 2024
Battery storage project J2109, St. James Parish County
Battery storage
25.0 MWWithdrawn / abandoned St. James Parish, LAMISO Aug 2021target 2025
Battery storage project J2012, Tangipahoa Parish County
Battery storage
20.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Nov 2021target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)