United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR Β· MISOSolar project J1959, St. John The Baptist Parish County
Solar project J1959, St. John The Baptist Parish County is a 100 MW solar request withdrawn in the MISO interconnection queue, in St. John The Baptist Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2021 (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1959
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Waterford-Vacherie 230kV
- Location
- St. John The Baptist Parish County, Louisiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 30 November 2021
- Proposed online date
- October 2025
- Withdrawn
- October 2023
Location
Marker shows the centre of St. John The Baptist Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in St. John The Baptist Parish County
- Solar project J3042, St. John The Baptist Parish CountySolar Β· 150 MW Β· in study
- Solar project J1797, St. John The Baptist Parish CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J1956, St. John The Baptist Parish CountyBattery storage Β· 60.0 MW Β· withdrawn
- Battery storage project J1958, St. John The Baptist Parish CountyBattery storage Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem