SOLAR Β· MISO

Solar project J1959, St. John The Baptist Parish County

Solar project J1959, St. John The Baptist Parish County is a 100 MW solar request withdrawn in the MISO interconnection queue, in St. John The Baptist Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1959
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Waterford-Vacherie 230kV
Location
St. John The Baptist Parish County, Louisiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
30 November 2021
Proposed online date
October 2025
Withdrawn
October 2023

Location

Marker shows the centre of St. John The Baptist Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in St. John The Baptist Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem