πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR + STORAGE Β· MISO

Solar + storage project J2245, St. Tammany Parish County

Solar + storage project J2245, St. Tammany Parish County is a 100 MW solar + storage request withdrawn in the MISO interconnection queue, in St. Tammany Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2245
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Mandeville - North Slidell 230kV Line (not listed on TTF, but both substations seem to have breakers
Location
St. Tammany Parish County, Louisiana
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
30 August 2021
Proposed online date
October 2024
Withdrawn
October 2023

Location

Marker shows the centre of St. Tammany Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in St. Tammany Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem