SOLAR + STORAGE Β· MISO

Solar + storage project J1674, St. Tammany Parish County

Solar + storage project J1674, St. Tammany Parish County is a 250 MW solar + storage request withdrawn in the MISO interconnection queue, in St. Tammany Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1674
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Talisheek - North Slidell 230kV Line
Location
St. Tammany Parish County, Louisiana
Technology
Solar: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 June 2020
Proposed online date
August 2023
Withdrawn
December 2020

Location

Marker shows the centre of St. Tammany Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in St. Tammany Parish County