SOLAR + STORAGE Β· MISO

Solar + storage project J3210, St. Tammany Parish County

Solar + storage project J3210, St. Tammany Parish County is a 100 MW solar + storage request withdrawn in the MISO interconnection queue, in St. Tammany Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3210
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
J2245 Substation
Location
St. Tammany Parish County, Louisiana
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
13 September 2022
Proposed online date
September 2025
Withdrawn
July 2025

Location

Marker shows the centre of St. Tammany Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in St. Tammany Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem