United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR Β· MISO

Solar project J1999, Rapides Parish County

Solar project J1999, Rapides Parish County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Rapides Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1999
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Rodemacher
Location
Rapides Parish County, Louisiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
21 December 2021
Proposed online date
October 2024
Withdrawn
March 2025

Location

Marker shows the centre of Rapides Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Rapides Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem