πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR Β· MISO

Solar project J1887, St. Martin Parish County

Solar project J1887, St. Martin Parish County is a 90.0 MW solar request withdrawn in the MISO interconnection queue, in St. Martin Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1887
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
St John 69kV
Location
St. Martin Parish County, Louisiana
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process
Queue status
Withdrawn
Entered queue
13 August 2021
Proposed online date
November 2024
Withdrawn
October 2021

Location

Marker shows the centre of St. Martin Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in St. Martin Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem