United States โ€บ Grid โ€บ Interconnection queues โ€บ Kansas

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Kansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown479,162 MW
Active in queue32.6 GW140 requests
Agreement signed9,162 MW47 requests
Withdrawn38780.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

47 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GEN-2020-007, Linn County
Solar + storage
650 MWAgreement signed Linn, KSSPP Apr 2020target 2028
Solar project GEN-2017-195, Johnson County
Solar
500 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Solar project GEN-2020-058, Finney County
Solar
425 MWAgreement signed Finney, KSSPP Apr 2020target 2028
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Solar project GEN-2017-184, Hodgeman County
Solar
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Solar + storage project GEN-2020-008, Stevens County
Solar + storage
250 MWAgreement signed Stevens, KSSPP Apr 2020target 2028
Solar + storage project GEN-2020-079, Cherokee County
Solar + storage
225 MWAgreement signed Cherokee, KSSPP Apr 2020target 2028
Solar project GEN-2018-057, Sedgwick County
Solar
203 MWAgreement signed Sedgwick, KSSPP May 2018target 2030
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2018-128, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2018target 2030
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Solar project GEN-2017-018, Barber County
Solar
189 MWAgreement signed Barber, KSSPP May 20172025
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Solar project GEN-2021-101, Douglas County
Solar
159 MWAgreement signed Douglas, KSSPP May 2021target 2027
Battery storage project GEN-2017-221, Sedgwick County
Battery storage
152 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Solar project GEN-2023-SR28, Ford County
Solar
150 MWAgreement signed Ford, KSSPP Oct 20232025
Solar project GEN-2019-055, Edwards County
Solar
150 MWAgreement signed Edwards, KSSPP May 2019target 2028
Solar project GEN-2019-058, Ford County
Solar
150 MWAgreement signed Ford, KSSPP May 2019target 2028
Battery storage project GEN-2021-103, Johnson County
Battery storage
150 MWAgreement signed Johnson, KSSPP May 2021target 2030
Onshore wind project GEN-2018-009, Seward County
Onshore wind
150 MWAgreement signed Seward, KSSPP Apr 2018target 2029
Solar + storage project GEN-2020-073, Franklin County
Solar + storage
150 MWAgreement signed Franklin, KSSPP Apr 2020target 2029
Battery storage project GEN-2017-196, Johnson County
Battery storage
128 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Solar project GEN-2018-049, Sumner County
Solar
120 MWAgreement signed Sumner, KSSPP May 2018target 2027
Solar project GEN-2017-068, Sumner County
Solar
104 MWAgreement signed Sumner, KSSPP May 2017target 2028
Solar project GEN-2019-044, Ford County
Solar
100 MWAgreement signed Ford, KSSPP May 2019target 2030
Battery storage project GEN-2018-108, Barber County
Battery storage
95.0 MWAgreement signed Barber, KSSPP Nov 2018target 2028
Onshore wind project GEN-2018-013, Dickinson County
Onshore wind
74.1 MWAgreement signed Dickinson, KSSPP Apr 2018target 2026
Solar project GEN-2017-022, Wilson County
Solar
65.0 MWAgreement signed Wilson, KSSPP May 2017target 2027
Gas project GEN-2020-003, Cowley County
Gas
58.0 MWAgreement signed Cowley, KSSPP Apr 2020target 2029
Battery storage project GEN-2019-053, Edwards County
Battery storage
50.0 MWAgreement signed Edwards, KSSPP May 2019target 2028
Battery storage project GEN-2019-063, Ford County
Battery storage
50.0 MWAgreement signed Ford, KSSPP May 2019target 2028
Solar project GEN-2021-SR8, Harper County
Solar
42.0 MWAgreement signed Harper, KSSPP May 20212023
Other project GEN-2024-GR4, Cherokee County
Other
27.1 MWAgreement signed Cherokee, KSSPP Jul 2024target 2026
Onshore wind project GEN-2019-001, Pratt County
Onshore wind
25.0 MWAgreement signed Pratt, KSSPP Nov 20182025
Solar project GEN-2020-056, Russell County
Solar
20.0 MWAgreement signed Russell, KSSPP Apr 20202025
Battery storage project GEN-2016-160, Ellis County
Battery storage
20.0 MWAgreement signed Ellis, KSSPP Nov 2016target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)