United States › Grid › Interconnection queues › Kansas
ONSHORE WIND · SPPOnshore wind project GEN-2018-009, Seward County
Onshore wind project GEN-2018-009, Seward County is a 150 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Seward County, Kansas, connecting to SUNC.
Queue statusConsented
- PlanningQueued Apr 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2018-009
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Cimarron 115kV Substation
- Location
- Seward County, Kansas
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 27 April 2018
- Proposed online date
- December 2029
Location
Marker shows the centre of Seward County; the queue data does not give exact sites.
Other requests in Seward County
- Solar + storage project GEN-2024-218, Seward CountySolar + storage · 199 MW · in study
- Onshore wind project GEN-2010-027, Seward CountyOnshore wind · 900 MW · withdrawn
- Onshore wind project GEN-2008-133, Seward CountyOnshore wind · 800 MW · withdrawn
- Onshore wind project GEN-2006-049, Seward CountyOnshore wind · 400 MW · withdrawn
- Solar + storage project GEN-2021-087, Seward CountySolar + storage · 100 MW · withdrawn
- Onshore wind project GEN-2008-080, Seward CountyOnshore wind · 80.0 MW · withdrawn
- Solar project GEN-2019-059, Seward CountySolar · 75.0 MW · withdrawn
- Solar project GEN-2020-082, Seward CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem