ONSHORE WIND · SPP

Onshore wind project GEN-2018-009, Seward County

Onshore wind project GEN-2018-009, Seward County is a 150 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Seward County, Kansas, connecting to SUNC.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-009
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Cimarron 115kV Substation
Location
Seward County, Kansas
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
27 April 2018
Proposed online date
December 2029

Location

Marker shows the centre of Seward County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Seward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem