United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

SOLAR Β· SPP

Solar project GEN-2019-059, Seward County

Solar project GEN-2019-059, Seward County is a 75.0 MW solar request withdrawn in the SPP interconnection queue, in Seward County, Kansas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedApr 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2019-059
Grid region
SPP (Southwest Power Pool)
Connection point (POI)
North Liberal 115kV substation
Location
Seward County, Kansas
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
22 May 2019
Proposed online date
December 2022
Withdrawn
April 2021

Location

Marker shows the centre of Seward County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Seward County