ONSHORE WIND Β· SPP

Onshore wind project GEN-2006-049, Seward County

Onshore wind project GEN-2006-049, Seward County is a 400 MW onshore wind request withdrawn in the SPP interconnection queue, in Seward County, Kansas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandonedOct 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2006-049
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Finney - Hitchland (Stevens County) 345kV
Location
Seward County, Kansas
Technology
Wind: 400 MW
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
18 December 2006
Proposed online date
December 2010
Withdrawn
October 2012

Location

Marker shows the centre of Seward County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Seward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem