United States › Grid › Interconnection queues › Kansas
SOLAR + STORAGE · SPPSolar + storage project GEN-2020-073, Franklin County
Solar + storage project GEN-2020-073, Franklin County is a 150 MW solar + storage request with a signed interconnection agreement in the SPP interconnection queue, in Franklin County, Kansas, connecting to KCPL.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-073
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KCPL
- Connection point (POI)
- SE Ottawa to Pleasant Valley 161kV
- Location
- Franklin County, Kansas
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 30 April 2020
- Proposed online date
- December 2029
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem