🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2018-049, Sumner County

Solar project GEN-2018-049, Sumner County is a 120 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Sumner County, Kansas, connecting to ITCGP.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-049
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Thistle 345kV Substation
Location
Sumner County, Kansas
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
29 May 2018
Proposed online date
April 2027

Location

Marker shows the centre of Sumner County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Sumner County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem