United States › Grid › Interconnection queues › Indiana
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Indiana (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Schahfer CCGTs Gas · NIPSCO |
2,740 MW | In study |
| Gas project J3999, Vermillion County Gas |
1,540 MW | In study |
| Malden CCGT Gas · NIPSCO |
1,090 MW | In study |
| Gas project AG2-072, Spencer County Gas · Bluegrass Power LLC |
700 MW | In study |
| Gas project J3084, Sullivan County Gas |
642 MW | In study |
| Malden BESS Battery storage · NIPSCO |
630 MW | In study |
| Merom Station Gas · Hallador Power |
530 MW | In study |
| Mitchell BESS Battery storage · NIPSCO |
527 MW | In study |
| Solar project J3931, Jasper County Solar |
500 MW | In study |
| Gas project J4005, Sullivan County Gas |
500 MW | In study |
| Gas project J4021, Sullivan County Gas |
470 MW | In study |
| Merom Storage Solar + storage · Hoosier Energy / Solvenz |
405 MW | In study |
| Solar project J3942, Vigo County Solar |
365 MW | In study |
| Solar project J3943, Vigo County Solar |
337 MW | In study |
| Brickyard Energy Storage Battery storage · Brickyard Energy Storge, LLC |
310 MW | In study |
| Solar + storage project J3114, Greene County Solar + storage |
300 MW | In study |
| Onshore wind project J3910, Newton County Onshore wind |
300 MW | In study |
| Onshore wind project J4063, Knox County Onshore wind |
300 MW | In study |
| Sandcut Storage Solar + storage · Hoosier Energy / Solvenz |
280 MW | In study |
| Onshore wind project J3846, Newton County Onshore wind |
275 MW | In study |
| Madison County Combustion Turbine Gas · Indiana Municipal Power Agency (IMPA) |
268 MW | In study |
| Solar project AG2-029, Noble County Solar · Southern Pike Solar LLC |
250 MW | In study |
| Solar project AG2-163, Fountain County Solar · Dolphin Solar LLC |
250 MW | In study |
| Solar project AG2-245, Starke County Solar · STARKE CENTRAL PROJECT, LLC |
210 MW | In study |
| Solar + storage project J3978, Sullivan County Solar + storage |
200 MW | In study |
| Solar + storage project J3980, Sullivan County Solar + storage |
200 MW | In study |
| Solar project J2538, Clark County Solar |
200 MW | In study |
| Solar + storage project J3981, Sullivan County Solar + storage |
200 MW | In study |
| Battery storage project J3948, Posey County Battery storage |
200 MW | In study |
| Solar project J2848, Hamilton County Solar |
200 MW | In study |
| Solar + storage project J3979, Sullivan County Solar + storage |
200 MW | In study |
| Surplus; J992 Battery storage |
200 MW | In study |
| Solar project J4039, Montgomery County Solar |
200 MW | In study |
| Solar project J4023, Clay County Solar |
185 MW | In study |
| Solar project AG2-230, St. Joseph County Solar · Dumont Solar, LLC |
150 MW | In study |
| Solar project AG2-637, Randolph County Solar · ACE Development Company, LLC |
150 MW | In study |
| Surplus Battery storage |
150 MW | In study |
| Solar + storage project AG2-126, Vermillion County Solar + storage · TGE Illinois 211, LLC |
150 MW | In study |
| Solar + storage project S1120, Knox County Solar + storage |
150 MW | In study |
| Battery storage project S1112, Pike County Battery storage |
130 MW | In study |
| Solar project AG2-491, White County Solar · Black Prairie Solar Park II LLC |
100 MW | In study |
| Battery storage project AG2-332, Elkhart County Battery storage · Amberjack Solar LLC |
100 MW | In study |
| Battery storage project AG2-343, Fountain County Battery storage · Dolphin Solar LLC |
100 MW | In study |
| Solar project AG2-550, Randolph County Solar · Riverstart Solar Park VI LLC |
100 MW | In study |
| Battery storage project AG2-248, Elkhart County Battery storage · Amberjack Solar LLC |
100 MW | In study |
| Replacing 100 MW of Solar with storage; J1386 Battery storage |
100 MW | In study |
| Surplus; J1190 Battery storage |
100 MW | In study |
| Solar project AH1-392, St. Joseph County Solar · ibV Energy Partners LLC |
90.0 MW | In study |
| Battery storage project AH1-482, Pulaski County Battery storage · Lightsource Renewable Energy Development, LLC |
78.0 MW | In study |
| Battery storage project AH1-302, Pulaski County Battery storage · Bottlebrush Solar Energy LLC |
75.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)