Withdrawn queue requests in California (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7120.4 GW
Active in queue4,783 MW20 requests
Agreement signed4,721 MW18 requests
Withdrawn7120.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

71 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Atlas
Solar + storage
2,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Gemini Wind North
Onshore wind
2,006 MWWithdrawn / abandoned CACAISO Apr 2018target 2025
Porthos Solar
Solar + storage
1,800 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Iron Hills Pumped Storage
Battery storage
1,407 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2025
Mercator
Solar + storage
1,037 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2021
Descendant Ranch 2
Solar + storage
1,024 MWWithdrawn / abandoned Colusa, CACAISO Apr 2018target 2023
Solar project 2018-G1
Solar
600 MWWithdrawn / abandoned CAWest Jun 2018target 2024
Castle Wind Offshore
Offshore wind
576 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2018target 2025
Rockfish Storage 1
Battery storage
510 MWWithdrawn / abandoned Monterey, CACAISO Apr 2018target 2023
Rockfish Storage 2
Battery storage
510 MWWithdrawn / abandoned Monterey, CACAISO Apr 2018target 2024
San Vicente Energy Storage Facility
Battery storage
500 MWWithdrawn / abandoned San Diego, CACAISO Apr 2018target 2025
Cortes
Battery storage
500 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2018target 2021
Sageberry Solar
Solar + storage
404 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Silverwing
Solar + storage
312 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Key Storage 2
Battery storage
309 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2024
Casy Solar
Solar + storage
308 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Mavericks
Battery storage
300 MWWithdrawn / abandoned Alameda, CACAISO Apr 2018target 2021
Placid
Solar + storage
270 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2021
Poseidon
Solar + storage
256 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2020
Arrow
Solar + storage
255 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2024
Solar + storage project Q66, Los Angeles County
Solar + storage
248 MWWithdrawn / abandoned Los Angeles, CAWest Dec 2018target 2021
Longspur 11
Solar + storage
234 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2022
Sagebrush Solar 5
Solar
224 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2022
Hood 2
Solar
220 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Hood 3
Solar
220 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Heartland 3
Solar + storage
206 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Del Rancho
Solar + storage
205 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2018target 2021
Green Mezzo
Battery storage
204 MWWithdrawn / abandoned Solano, CACAISO Apr 2018target 2022
Hudson Solar 2
Solar + storage
204 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Black Diamond Energy Storage 2
Battery storage
200 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2018target 2021
Moorhen Energy Storage
Battery storage
200 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2018target 2022
Big Bear Wind
Onshore wind
199 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2018target 2022
Tepona Off-Shore Wind
Offshore wind
162 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2018target 2034
Stargaze Solar BESS
Solar
154 MWWithdrawn / abandoned Alameda, CACAISO Apr 2018target 2021
Limon Energy Park
Solar + storage
153 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2020
Falcon Energy Center
Battery storage
151 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2018target 2021
Windcharger ESS
Battery storage
150 MWWithdrawn / abandoned Solano, CACAISO Apr 2018target 2021
Highline Solar Energy Center
Solar + storage
120 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2021
Hood 1
Solar
110 MWWithdrawn / abandoned Tulare, CACAISO Apr 2018target 2022
DRY Creek Solar
Solar
110 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2022
Dernopi Solar
Solar
103 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2021
Stephen
Solar
103 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Poleline Solar Energy Center
Solar + storage
102 MWWithdrawn / abandoned Merced, CACAISO Apr 2018target 2021
Mammoth Energy Storage
Battery storage
101 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2021
Pintail Energy Storage
Battery storage
100 MWWithdrawn / abandoned Sonoma, CACAISO Apr 2018target 2021
Temettate Advanced Caes
Battery storage
100 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2018target 2024
Mcgrath Energy Center 1
Battery storage
100 MWWithdrawn / abandoned Ventura, CACAISO Apr 2018target 2020
Hydaspes
Solar + storage
82.0 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Windy Wash Solar
Solar
79.0 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Gonzaga Ridge Wind Farm 3
Onshore wind
76.0 MWWithdrawn / abandoned Merced, CACAISO Apr 2018target 2020
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)