United States › Grid › Interconnection queues › California
BATTERY STORAGE · CAISOMcgrath Energy Center 1
Mcgrath Energy Center 1 is a 100 MW battery storage request withdrawn in the CAISO interconnection queue, in Ventura County, California, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2018 (completed)
- Withdrawn / abandonedFeb 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1515
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Mandalay-Santa Clara 220kV
- Location
- Ventura County, California
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 16 April 2018
- Proposed online date
- December 2020
- Withdrawn
- February 2019
Location
Marker shows the centre of Ventura County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Ventura County
- Drifter Energy StorageBattery storage · 505 MW · agreement signed
- Goldback Solar CenterBattery storage · 500 MW · agreement signed
- Shoals Energy StorageBattery storage · 409 MW · agreement signed
- Rosa StorageBattery storage · 512 MW · in study
- Ventura Clean EnergyGas · 778 MW · withdrawn
- Edison Drive Energy StorageBattery storage · 672 MW · withdrawn
- Gwent Storage 2Battery storage · 473 MW · withdrawn
- Mission RockGas · 326 MW · withdrawn
- Ventura Energy CenterGas · 326 MW · withdrawn
- Mission Rock Energy Center (Fka Mission Rock Energy Center Flex)Gas · 305 MW · withdrawn
- MichelangeloBattery storage · 205 MW · withdrawn
- WP Goleta (Fka WP Oxnard)Gas · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem