πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Hood 1

Hood 1 is a 110 MW solar request withdrawn in the CAISO interconnection queue, in Tulare County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1498
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Olive Switching Substation 115kV
Location
Tulare County, California
Technology
Solar: 110 MW
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 April 2018
Proposed online date
December 2022
Withdrawn
March 2019

Location

Marker shows the centre of Tulare County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Tulare County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem