Rexford Solar Farm

Rexford Solar Farm is a 540 MW solar + storage request built and operating in the CAISO interconnection queue, in Tulare County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedJul 2020 (completed)
  3. Construction (completed)
  4. OperatingNov 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1516
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vestal Substation 230kV
Location
Tulare County, California
Technology
Solar: 300 MW · Battery: 240 MW
Total requested
540 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
16 April 2018
Agreement signed
2 July 2020
Proposed online date
October 2022
Came online
November 2025

Location

Marker shows the centre of Tulare County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Tulare County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem