πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· WEST

Solar project 2018-G1

Solar project 2018-G1 is a 600 MW solar request withdrawn in the West interconnection queue, connecting to WAPA Sierra Nevada.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2018-G1
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Sierra Nevada
Connection point (POI)
Dos Amigos 230 kV Substation
Location
California
Technology
Solar: 600 MW
Total requested
600 MW
Study phase
Withdrawn by Customer via email on 11/2/22.
Queue status
Withdrawn
Entered queue
5 June 2018
Proposed online date
April 2024

Location

No county location in the queue data.

Power plants in California Β· Transmission lines in California

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem