Gas project LGE-GIS-2022-003, Jefferson County Gas |
660 MW | Agreement signed |
Jefferson, KY | Southeast |
Jun 2022 | target 2027 |
Pepper Hammock 500 Solar Solar |
500 MW | In study |
Glynn, GA | Southeast |
Jul 2022 | target 2024 |
Solar project IC-1084, Coweta County Solar |
470 MW | Paused / redesign |
Coweta, GA | Southeast |
Oct 2022 | target 2027 |
Gas project GI-104, Payne County Gas |
460 MW | Agreement signed |
Payne, OK | Southeast |
Jul 2022 | target 2026 |
Gas project GI-103, Creek County Gas |
460 MW | Agreement signed |
Creek, OK | Southeast |
Jul 2022 | target 2027 |
Gas project GI-101, Clinton County Gas |
460 MW | Agreement signed |
Clinton, MO | Southeast |
Jul 2022 | target 2027 |
Solar + storage project IC-1059, Pike County Solar + storage |
420 MW | Paused / redesign |
Pike, AL | Southeast |
Sep 2022 | target 2027 |
Battery storage project IC-1102, Montgomery County Battery storage |
400 MW | Paused / redesign |
Montgomery, AL | Southeast |
Dec 2022 | target 2026 |
Solar project IC-1071, Perry County Solar |
336 MW | Agreement signed |
Perry, AL | Southeast |
Sep 2022 | target 2027 |
Battery storage project IC-1091, Mobile County Battery storage |
300 MW | Paused / redesign |
Mobile, AL | Southeast |
Nov 2022 | target 2027 |
Rock House Solar Solar + storage |
250 MW | In study |
Mcduffie, GA | Southeast |
Jan 2022 | target 2025 |
Solar project IC-1014, Jeff Davis County Solar |
230 MW | Paused / redesign |
Jeff Davis, GA | Southeast |
Jan 2022 | target 2025 |
Solar project IC-1098, Taylor County Solar |
225 MW | Paused / redesign |
Taylor, GA | Southeast |
Nov 2022 | target 2027 |
Pepper Hammock Solar Solar |
200 MW | In study |
Glynn, GA | Southeast |
Jun 2022 | target 2024 |
Solar project 512, Lee County Solar |
200 MW | In study |
Lee, MS | Southeast |
Aug 2022 | target 2028 |
Solar + storage project IC-1013, Oglethorpe County Solar + storage |
200 MW | Paused / redesign |
Oglethorpe, GA | Southeast |
Jan 2022 | target 2025 |
Solar project IC-1088, Lee County Solar |
200 MW | Agreement signed |
Lee, GA | Southeast |
Nov 2022 | target 2027 |
Solar project IC-1097, Emanuel County Solar |
200 MW | Agreement signed |
Emanuel, GA | Southeast |
Nov 2022 | target 2028 |
Solar project IC-1094, Irwin County Solar |
200 MW | Agreement signed |
Irwin, GA | Southeast |
Nov 2022 | target 2028 |
Solar + storage project IC-1042, Rockdale County Solar + storage |
200 MW | Paused / redesign |
Rockdale, GA | Southeast |
Jul 2022 | target 2026 |
Solar project IC-1055, Coffee County Solar |
200 MW | Agreement signed |
Coffee, GA | Southeast |
Aug 2022 | target 2027 |
Battery storage project 514, Dekalb County Battery storage |
200 MW | Agreement signed |
Dekalb, AL | Southeast |
Aug 2022 | target 2028 |
Battery storage project 567168, Mecklenburg County Battery storage |
197 MW | In study |
Mecklenburg, NC | Southeast |
Jun 2022 | target 2029 |
Solar + storage project IC-1040, Hale County Solar + storage |
170 MW | Paused / redesign |
Hale, AL | Southeast |
Jun 2022 | target 2027 |
Crawford Solar Solar + storage |
160 MW | In study |
Crawford, GA | Southeast |
Jun 2022 | target 2025 |
Solar + storage project IC-1100, Pulaski County Solar + storage |
150 MW | Paused / redesign |
Pulaski, GA | Southeast |
Nov 2022 | target 2026 |
Solar + storage project IC-1101, Perry County Solar + storage |
150 MW | Paused / redesign |
Perry, AL | Southeast |
Dec 2022 | target 2027 |
Solar project IC-1037, Taliaferro County Solar |
150 MW | Paused / redesign |
Taliaferro, GA | Southeast |
May 2022 | target 2026 |
Solar project 501, Bledsoe County Solar |
150 MW | Agreement signed |
Bledsoe, TN | Southeast |
May 2022 | target 2025 |
Ocilla Solar Solar |
150 MW | In study |
Irwin, GA | Southeast |
Nov 2022 | target 2025 |
Solar project IC-1044, Laurens County Solar |
150 MW | Agreement signed |
Laurens, GA | Southeast |
Jul 2022 | target 2027 |
Solar + storage project IC-1099, Pulaski County Solar + storage |
150 MW | Paused / redesign |
Pulaski, GA | Southeast |
Nov 2022 | target 2026 |
Solar project IC-1015, Mitchell County Solar |
150 MW | Paused / redesign |
Mitchell, GA | Southeast |
Jan 2022 | target 2027 |
Brenneman Solar Solar |
150 MW | In study |
Macon, GA | Southeast |
Nov 2022 | target 2024 |
Solar project 510, Carroll County Solar |
140 MW | Agreement signed |
Carroll, TN | Southeast |
Jul 2022 | target 2029 |
Meriwether Panther Solar Solar + storage |
125 MW | In study |
Meriwether, GA | Southeast |
Jan 2022 | target 2026 |
Solar + storage project IC-1068, Emanuel County Solar + storage |
124 MW | Agreement signed |
Emanuel, GA | Southeast |
Sep 2022 | target 2027 |
Solar project IC-1038, Ware County Solar |
120 MW | Paused / redesign |
Ware, GA | Southeast |
May 2022 | target 2026 |
Battery storage project 563648, Gaston County Battery storage |
115 MW | In study |
Gaston, NC | Southeast |
Jun 2022 | target 2027 |
Solar project IC-1074, Turner County Solar |
111 MW | Paused / redesign |
Turner, GA | Southeast |
Oct 2022 | target 2025 |
Solar project IC-1067, Treutlen County Solar |
111 MW | Paused / redesign |
Treutlen, GA | Southeast |
Sep 2022 | target 2026 |
Two Rivers Solar Solar + storage |
102 MW | In study |
Camden, GA | Southeast |
Mar 2022 | target 2027 |
Solar project IC-1043, Coosa County Solar |
100 MW | Paused / redesign |
Coosa, AL | Southeast |
Jul 2022 | target 2030 |
Solar project IC-1035, Heard County Solar |
100 MW | Paused / redesign |
Heard, GA | Southeast |
May 2022 | target 2025 |
Solar + storage project IC-1072, Marengo County Solar + storage |
80.0 MW | Paused / redesign |
Marengo, AL | Southeast |
Oct 2022 | target 2027 |
Solar + storage project IC-1054, Pike County Solar + storage |
80.0 MW | Paused / redesign |
Pike, AL | Southeast |
Aug 2022 | target 2027 |
Solar project IC-1066, Dale County Solar |
80.0 MW | Paused / redesign |
Dale, AL | Southeast |
Sep 2022 | target 2030 |
Solar project 568986, Person County Solar |
80.0 MW | Agreement signed |
Person, NC | Southeast |
Jun 2022 | target 2027 |
Solar project IC-1051, Escambia County Solar |
80.0 MW | Paused / redesign |
Escambia, AL | Southeast |
Aug 2022 | target 2027 |
Solar project IC-1083, Marengo County Solar |
80.0 MW | Paused / redesign |
Marengo, AL | Southeast |
Oct 2022 | target 2026 |