United States › Grid › Interconnection queues › Tennessee
SOLAR · SOUTHEASTSolar project 501, Bledsoe County
Solar project 501, Bledsoe County is a 150 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Bledsoe County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 501
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Great Falls HP - Spring City 161-kV TL
- Location
- Bledsoe County, Tennessee
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 23 May 2022
- Proposed online date
- February 2025
Location
Marker shows the centre of Bledsoe County; the queue data does not give exact sites.
Other requests in Bledsoe County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem